Home  
   Wanted
   Ancillaries
   

Siemens-V64.3-50hz-69mw
Siemens V64.3 Gas Turbine Power Plant, 69 MW, 50 hz, 11 kv. Plant commissioned 1994. Since new 8191 total hours. 1307 starts. Used for peaking 1000 hours per year contract is done. Dual fuel currently running on liquid. Complete Ebara water demin plant and step-up transformer 66kv included. Full borescope report at 8000 hours available. Includes BOP, spares, full history. Terms FOB on vessel in port.

previous | index | next View original | 179.2 KB
plant-layout.jpg
For Sale
Siemens V64.3 Gas Turbine Power Plant, 69 MW, 50 hz, 11 kv, 9000 total hours since new, includes BOP, spares, full history. Terms FOB.
Roark Edwards 612-424-9660