Siemens V64.3 Gas Turbine Power Plant, 69 MW, 50 hz, 11 kv. Plant commissioned 1994. Since new 8191 total hours. 1307 starts. Used for peaking 1000 hours per year contract is done. Dual fuel currently running on liquid. Complete Ebara water demin plant and step-up transformer 66kv included. Full borescope report at 8000 hours available. Includes BOP, spares, full history. Terms FOB on vessel in port.